Timeline of the Attack Helicopter Project
« on: November 16, 2013, 02:46:25 am »


• 29 Jul 2013: Agusta Westland AW-109 declared as Single Calculated Bid subject to PQ
• 08-14 Sep 2013: PQ conducted
• 23 Sep 2013: TWG presented the PQ Report to SBAC1
• 27 Sep 2013: SBAC1 declared Agusta as SCRB:
• 07 Oct 2013: NOA issued
• 11 Oct 2013: Start of Contract formulation
• 16 Oct 2013: SBAC1 Discussion: Focused on the additional fuel cell & complete Precision Guided Munitions capability.
• 17 Oct 2013: Initial Contract signing
• 29 Oct 2013: Contract signed by CSAFP
• Contract for signature of SND

Projected Delivery

2014 (2) - 2015 (6)
(2) 365 calendar days/12 mos after LC opening
(4) 450 calendar days/15 mos after LC opening
(2) 540 calendar days/18

http://goo.gl/lJQI7M