 Picture above isnt the actual project, but merely demonstrating what an aircraft hangar looks like (for those who don't know)

• 29 Aug 2013: J4/TCE-evaluated decision package forwarded to OASAIL
• 24 Sep 2013: Discussion on procurement of infastructure projects with ASAIL
• 01 Oct 2013: ADM issued
• 16 Oct 2013: Initial presentation to SBAC2
• 17 Oct 2013: ICT review of bid docs at DAO, DND with TWG.
• 24 Oct 2013: Continuation of ICT review of Bid Docs/GHQ BAC2 Pre-Procurement Conference
• 31 Oct 2013: ITB published
• 11 Nov 2013: Pre Bid Conf
• 25 Nov 2013: Bid opening

Projected Delivery

2014
10 months after issuance of NTP