• 22 Sep 2013: ITB published
• 30 Sep 2013: Pre-bid conference (3 prospects)
• 07 Oct 2013: SBAC1 granted the request to extend Bid Opening by 2 weeks fm 14 Oct 13
• 21 Oct 2013: SBAC1 further moved the Bid Opening for another 3 weeks as a result of the discussion on the queries of the proponents
.• 04 Nov 2013: The TWG presented the answers to queries raised by proponents, the Committee made some corrections for submission by the TWG, afterwhich the DND BAC will distribute the supplemental bid bulletin to concern proponents.
• 06 Nov 2013: Preparation of Supplemental Bid Bulletin at DAO, DND.
• 11 Nov 2013: Bid Opening
Projected Delivery
2015 (2) - 2016 (1)
(1) 18 months after LC opening
(1) 22 months after LC opening
(1) 26 months after LC opening
http://goo.gl/lJQI7M