• 24 Jul 13: Pre-negotiation started
• 16 Aug 2013: TWG presentation of pre-nego status to SBAC1
• 22 Aug 2013: P&A for 14 EGI released by JUSMAG
• 17-19 Sep 2013: Meeting with FMS GPS Directorate @ OA-4 to craft LOR for LOA
• 01-02 Oct 2013: Resumption SBAC1 Pre-negotiation with KAI
• 14 Oct 2013: Consultative Meeting @ Malacanang to discuss the method of procurement whether thru Sec 4 or Sec 53.8 of the IRR of RA 9184
• 23 Oct 2013: SBAC1 discussion on the technical issues
• 24 Oct 2013: SBAC1 discussion on legal, financial, technical & other issues23,24 & 25 Oct 13 - Pre Nego at DND* For formal negotiation on 29 & 30 Oct 13* Conduct of PQ by 1st week of Nov
• 29-30 Oct 13: Negotiation Proper at DND BAC
• 05-06 Nov 2013: Continuation of Pre Nego with KOTRA.
Projected Delivery
2016 (2)- 2017 (6)- 2018 (4) BFEs via FMS:
22 mos(2) 18 months after LC opening
(2) 30 months after opening of LC then
(2) every 2 months thereafter until completed